Project File:

Lidgard House Wharf Refurbishment

Client
Client – RNZYS
Contact – Craig Peploe
Title – General Manager
Phone - +64 9 3606800

Location
Kawau Island
36° 83' S 175° 70' E

Time Period
Nov 2010 - Nov 2010

 

Project Description


The existing wooden wharf structure outside Lidgard House had deteriorated over time and was deemed unsafe. TMS were engaged to refurbish/rebuild a new wooden wharf to ensure the safety of any users. TMS undertook the responsibility to construct and design the wharf to ensure that it could be constructed within a realistic timeframe and met the necessary safety provisions.

Performance


The entire project was completed within 3 weeks and ready for the holiday boaties visiting the island over the 2010/2011 summer. The client's feedback was complimentary on the overall timeframe taken to complete the project and TMS's care and attention to detail.

The new Wharf and the refurbishment of the existing gangway and floating pontoon will ensure the RNZYS will continue to provide safe mooring and docking facilities for a further 30-40 years.

Physical Works

  • Demolition of the existing fixed wooden wharf structure
  • Remove existing gangway and floating pontoon to be re-installed when the fixed wooden structure is completed.
  • Drive new wooden piles to support walkway and landing structure.
  • Construct new walkway, handrail, toe rail and stairs.